The financial success of a renewable energy power plant depends on the accuracy of site analyses, land selection and administrative permitting decisions made at the concept stage. We manage every step — from grid connection capacity research to Industrial Registry Certificate — under one roof.
Full regulatory compliance with Turkish renewable energy legislation — complete chain of responsibility through to Ministry acceptance. Backed by 1 GW+ of portfolio experience in the field.
Investigation of grid connection capacity and determination of the land's legal status. The most critical first step influencing the entire project lifecycle.
Preparation of licensed and unlicensed generation applications and management of capacity tender processes.
Topographic and geological surveys on site. Installation of TSMS (Turkish State Meteorological Service)-approved wind measurement infrastructure for WPP projects.
Environmental Impact Assessment and zoning plan preparation. Collection of positive opinions from 20+ public authorities.
Preparation of production simulations and electromechanical designs, followed by obtaining official project approvals.
Obtaining the construction permit and completing Tier-1 equipment procurement along with site assembly.
Legal completion of the project — final steps from MENR (ETKB) acceptance through to the Industrial Registry Certificate.
We manage all processes with EMRA (EPDK), MENR (ETKB), TEİAŞ, TEİAŞ/TEDAŞ, DSI, the Ministry of Agriculture & Forestry and the Ministry of Environment at the technical standards required by each authority.
We do not deliver our project development service piecemeal — we take complete responsibility from land registration through to Industrial Registry, as a single authorised point of contact.
Particularly across Eastern Europe and beyond, we structure project infrastructure compliant with global grid and financing standards (IEC, EU Grid Codes).
For each development stage: the relevant public authority, regulatory basis and official document obtained.
| Development Stage | Relevant Public Authority | Key Regulation | Document Obtained |
|---|---|---|---|
| 01. Capacity & Land | TEİAŞ / TEDAŞ / Treasury / Provincial Agriculture | RES Law, Land Conservation Law | Capacity & Land Status Report |
| 02. Capacity Allocation | MENR / EMRA / EDAS | Unlicensed / Licensed Regulation | Call Letter / Grid Connection Agreement |
| 03. Site Surveys | Ministry of Environment & Urbanisation / TMMOB | Measurement Standards Communiqué | Approved Geological Survey & Wind Measurement Report |
| 04. EIA & Zoning | Governorship / Municipality / Special Provincial Administration | EIA Regulation, Zoning Law No. 3194 | EIA Positive Decision & Approved Zoning Plan |
| 05. Engineering Design | MENR / TEDAŞ | Project Approval Regulation | Officially Approved Electrical & Mechanical Projects |
| 06. EPC & Construction | MENR / Municipality / Special Provincial Administration | Zoning Law / Regulations | Construction Permit & Site Assembly Acceptance |
| 07. Official Acceptance & Registry | MENR | MENR Acceptance Regulation | Ministry Acceptance Minutes & Industrial Registry Certificate |